Ducted in Jamaica Plain
This Jamaica Plain triple-decker already had ductwork running through all three units, fed by three gas furnaces in the basement. That made it a straightforward candidate for a ducted swap: keep the ducts, replace each furnace with a heat pump air handler, and give every floor central heating and air conditioning on electricity.
The design
Each unit got its own Mitsubishi system: an SVZ-AP18NL multi-position air handler in the basement where the furnace used to be, paired with an 18k SUZ-AA18NLHZ Hyper-Heat outdoor unit. That's three air handlers and three condensers in all, one of them wall-bracketed under the back porch.
The building's load is modest, roughly 15,000 BTU per floor at design conditions, so the equipment has comfortable headroom. Before committing to the existing ducts, we ran a Manual D verification to confirm they could move the airflow these air handlers need. The ducts are old but insulated and in good shape, and they're sized well enough that the air handlers can run at mostly medium fan speed. We added a new supply branch to the first-floor kitchen, replaced return grilles, and sealed registers throughout.
Electrical capacity was the other constraint. Three heat pumps on a 200 A service is tight, so we chose Mitsubishi in part because its air handlers don't need a dedicated breaker of their own, and we installed a Stepwise load-management device that sequences loads so the building never exceeds its 200 A service.
The install
The crew completed the swap over one week in mid-October. Because this is old ductwork, we followed up with a static pressure test on each system to confirm the ducts were performing as designed, and the numbers checked out.
Jamaica Plain triple-decker with existing ductwork and three gas furnaces in the basement, one per unit, on a 200 A electrical service.
3 Mitsubishi SVZ-AP18NL air handlers paired with 3 SUZ-AA18NLHZ Hyper-Heat outdoor units, reusing the existing ducts after a Manual D verification, plus a new kitchen supply, register sealing, and a Stepwise load-management device to stay within the 200 A service.
Completed in about a week in October 2026. Post-install static pressure tests confirmed the existing ducts perform well, with the air handlers running mostly at medium fan speed.