Heat Pump + HPWH in East Boston
This East Boston triple-decker wanted to go fully electric. The building had been running on combination boilers, and the homeowner was taking part in MassCEC's Triple Decker Challenge to electrify the whole thing. It was our first time taking on an entire triple-decker, and we learned enough that we wrote a full research article about it: The Triple Decker Guide to Heat Pumps.
The design
Each floor had four zones, which made Daikin's Aurora cold-climate MXL multi-zone heat pumps a natural fit: one outdoor unit per floor, three in total, each running four indoor heads. There's no ductwork anywhere in the building. In a triple-decker you can't run ducts through an empty attic or basement the way you might in a single-family home, so a ductless design kept things straightforward.
We also replaced water heating with three heat pump water heaters, one for each unit.
The install
We got lucky on layout: all three floors share the same floor plan. That meant we could stack and consolidate the refrigerant lines from the third floor straight down to the first, which made for a very clean look on the side of the house.
Because this was a winter job, it took about 10 working days, or roughly two weeks on the calendar.
East Boston triple-decker rental heated by combination boilers, going fully electric as part of MassCEC's Triple Decker Challenge. A 400 amp service upgrade was completed the month before.
3x Daikin Aurora cold-climate 4MXL36WVJU9 outdoor units, one per floor, each serving four ductless zones. 3x Bradford White heat pump water heaters installed in the basement.
Winter install completed in about 10 working days (roughly two weeks). Identical floor plans let us consolidate line sets from all three floors into one clean run down the side of the house. Full notes in Laminar Collective's triple-decker heat pump guide.